Completed Projects


Recently Completed Projects

 Water Infrastucture 

Ipswich City Council Leakage and Pressure Management (Package 5)

  • Installation of Flow Meters and Pressure Reducing Valves
  • Concrete Pit Work 
  • Pressure Testing 
  • Live Connection 

Total Project Value of $1,000,000.00

 


Origin Alliance (Dinmore to Goodna)

  • Water Main Relocation
  • Property Connections and Water Meter Replacement
  • Concrete Pit Work 
  • Pressure Testing 
  • Live Connection 

Total Project Value of $600,000.00

 


Eastern Bus Way Project (Leighton Contractors)

  • Water Main Relocation
  • Property Connections and Water Meter Replacement
  • Concrete Pit Work 
  • Pressure Testing 
  • Live Connection 

Total Project Value of $500,000.00

 


Mt Crosby Trunk Water Main Connection to SRWP Pipeline 

  •  DN500 MSCL Water Main Installation
  • Valve Pit and Thrust Block Construction
  • Concrete Pit Work 
  • Pressure Testing 
  • Live Connection 

Total Project Value of $500,000.00

 


Merrimac Waste Water Treatment Plant  

  • DN1610 MSCL Water Main Installation
  • Valve Pit and Thrust Block Construction
  • Concrete Pit Work 
  • Pressure Testing 
  • Live Connection 

Total Project Value of $500,000.00

 


Port of Brisbane

  • Water and Fire Reticulation (150-300mm Dia. HDPE)
  • Valve and Pit Installation 

Total Project Value of $1,000,000.00

 


 Stormwater Infrastructure 

Fulton Hogan Pacific Motorway Upgrade

  • Installation of pump stations and commissioning of sewer/drainage systems for buildings.
  • Installation of Fire main, Sewer Main, Non Potable and Potable water lines

Origin Alliance (Dinmore to Goodna) – Abi Group

  • Twin DN1650 Installation
  • Jacking of 1650 Pipeline
  • Ecosoil Systems
  • Maintenance Shaft Construction

Total Project Value of $480,000.00

 


Eastern Bus Way Project (Leighton Contractors)

  • 3.8m x 4m RCBC Pipeline Construction
  • 2700mm Pipeline Construction
  • Ecosoil Systems
  • Concrete Super Structures 
  • Tidal Management
  •  Live Connection 

Total Project Value of $1,300,000.00

 


Logan – Ipswich Interchange Project  (Leighton Contractors)

  • DN1800 RCBC Installation
  • DN3000 Pipeline Construction
  • Jacking of 1800 Pipeline 
  • Concrete Pit Work 

Total Project Value of $700,000.00

 


Merrimac Waste Water Treatment Plant  (John Holland)

  • DN1650 RCP Over Flow and Discharge Line
  • Stormwater Harvesting and Treatment
  • DN1800 Ecosoil Systems 
  • Valve Pit and Thrust Block Construction
  • Concrete Pit Work 
  • Pressure Testing 
  • Live Connection 

Total Project Value of $500,000.00

 


Various Developments for Delfin, Pensar and Civdec 

  • Sub Divisional Drainage
  • Concrete Pit Work
  • Culvert Installation

 


Gold Coast Desalination Alliance 

  • Roads and Stormwater Drainage

Total Project Value of $2,000,000.00


 

 Sewage Infrastructure 

Gallipoli Army Barracks Upgrade

  • Installation of underground service networks including Natural Gas and Firefighting/Potable/Recycled Water
  • Installation of HV and communication conduits, SCEC pits and upgrading of existing pits
  • Installation of a fire fighting system including multiple pump sets, H-patterns and double pillar fire hydrants pump stations
  • Installation of Flow Meter Pits, Reduced Pressure Zone Arrangements, Reflux/Check Valve arrangements

Total Project Value of $11.5 million

Gold Coast Desalination Alliance 

  • Plumbing of Complex Filtration Systems
  • Chemical Dosing Facilities 

Total Project Value of $1,000,000.00

 


Ipswich City Council G12 Pump Station Modifications 

  • Installation of Bypass Line
  • Permanent DN1350 Pipe Work Installation  
  • Valve and Valve Pit Construction
  • Wet Well Construction and Storage Facility
  • Pump Station Fit-out  
  • Pressure Testing 
  • Live Connection 

Total Project Value of $500,000.00

 


Origin Alliance (Dinmore to Goodna)

  • DN900 Plasti-Line Sewer Relocation
  • Maintenance Shaft Construction
  • Bypassing of Live Sewer
  • Pressure Testing 
  • Live Connection 

Total Project Value of $280,000.00

 


Eastern Bus Way Project (Leighton Contractors)

  • DN800 PE Pipeline Relocation
  • Property Connections and Water Meter Replacement
  • Concrete Pit Work 
  • Pressure Testing 
  • Live Connection 

Total Project Value of $400,000.00

 


Merrimac Waste Water Treatment Plant  

  • DN1350 MSCL Pipework Installation
  • Construction of Pump Station 
  • Pump Station Fit-out 
  • Concrete Pit Work 
  • Pressure Testing 
  • Live Connection 

Total Project Value of $500,000.00

 


Gold Coast Desalination Alliance  

  • Internal and External Gravity Sewers (HDPE)
  • Reinforced Concrete Pit Construction
  • All Under Slab Drainage

Total Project Value of $2,000,000.00

 


G12 Sewer Pump Station  

  • Twin DN1800 RCP Inlet Works
  • DN1350 Bypass and Flow Control
  • DN600 MSCL Rising Main
  • Concrete Valve Pits and Thrust Blocks
  • Outlet and Over Flow Works 
  • Pump Station and Pump Station Fit-out and Live Connections 
  • Flow Meter Installation

 Civil Structures 

Merrimac Waste Water Treatment Plant

  • Construct Reinforced Concrete Water Storage Tanks
  • Construct Concrete Valve and Flow Meter Pits

Total Project Value of $500,000.00

 


Ipswich City Council Leakage and Pressure Management

  • Construct Reinforced Concrete PRV and Flow Meter Pits
  • Install Semi-Precast Concrete Pits

Total Project Value of $1,000,000.00

 


Eastern Bus Way Project (Leighton Contractors)

  • Construct Reinforced Concrete Stormwater Super Structures
  • Construct Large Scale Reinforced Concrete Sewer Chambers

Total Project Value of $400,000.00

 


 Water, Sewage and Stormwater 

Goodna Sewerage Treatment Plant Upgrade

  • Installation of Pipelines ranging from 1440mm in diameter down to 32mm
  • Installation of HV, LV and communication conduits, Pits and Rubble drains
  • Importing over 40,000 tonne (16,000m³ Compacted) of fill in and around structures throughout the project.
  • Installation of Chemical dosing lines within enveloper pipes, Install of the termination points and leak sumps.
  • Managing flow controls and performing live connections into existing infrastructure
  • Installation of Manholes, Scour pits, Chemical termination points

Total Project Value of $4.5 million